Main menu:
Projects > Civil Engineering (Marine & Coastal) Projects
| INISHBOFIN COASTAL PROTECTION WORKS & PIER IMPROVEMENT WORKS, Inishbofin, Co. Galway. |
Construction of a new 90m long sheet pile pier, 300m long retaining sea wall in precast and in-situ concrete, the dredging of approximately 30,000m3 of silt, sand and gravel with deposition behind the concrete retaining wall and the formation of a slope between the top of the wall and the top of the existing cliffs. The work was topped with a precast revetment surface. Improvement works were also carried out to the existing quay, including provision of a new slipway. Because of the location of the project on an offshore island, significant logistical obstacles had to be overcome, including extensive off site pre-casting, on site concrete production, and restricted plant availability. The dredge element was heavily restricted by environmental considerations, which imposed severe limitations on the methodology to bring the dredged material ashore. To execute this piece of the work L&M Keating Ltd acquired a unique piece of dredge plant from the USA, (a Versi Dredge 7012), and the dredge material was pumped ashore from the floating plant. Part of the dredged material had to be dumped at sea. This dredging was carried out using a back-hoe on a jack up barge and the material brought to sea via a split bottom barge. The existing old pier was refurbished. Works involved the installation of new pre-cast pier face elements. The existing pier deck was then refurbished and a new in-situ concrete deck was constructed. Extensive repairs to traditional stone pier structure which included replacement of stone elements and re-grouting of joints. The existing “new pier” was also refurbished. Works involved the installation of a sheet-piled wall around the existing pier which was then tied into the existing structure. This was then in filled with dredged material and a new concrete deck and steps constructed. This element was constructed on a design build basis. A passive cathodic protection system was installed. The M&E package included the installation of public lighting, navigation beacons and hydraulic crane. L&M Keating Ltd executed all piling works by mobilising company owned resources to the island by barge. |
| Client | Galway County Council, County Buildings, Prospect Hill, Galway. |
| Consulting Engineers | RPS Consulting Engineers, Elmwood House, 74 Boucher Road, Belfast, BT12 6RZ. |
| Value | €7m |
Sub-Menu: